Total Pageviews

Sunday, June 21, 2020

The Virginia Bath County Pumped Storage Station

There are nearly 
300 pumped storage 
projects in the world, 
and 40 in the United 
States. 

The facility 
in Bath County 
Virginia is the 
largest one now, 
-- it can generate 
3,003MW 
(megawatts) 
when all six
generators 
are operating 
at full power.

Within the 
United States, 
only Grand
Coulee Dam 
has more capacity 
to generate electricity
fro, flowing water. 

A 4,000MW project 
at Lake Revelstoke 
in British Columbia 
has been proposed. 

In 2017 the largest 
pumped storage 
in Europe was the 
Cortes-La Muela 
hydroelectric project 
in Spain, which was 
rated  at 1,762MW. 

The largest in China 
was the Cuntangkou 
Pumped Hydro Power 
Station in Sichuan, 
rated at 2,000MW

The Snowy Hydro 2.0 
pumped storage project 
in Australia completed 
a feasibility study in 2017 
that proposed to expand 
the existing network 
of hydropower dams 
to provide up to 
6,000MW of electricity
generating capacity. 



At the Bath County Virginia
Pumped Storage Station, 
Dominion Energy moves 
water between their
uphill and downhill
reservoirs, to create 
a "giant battery", 
for providing electricity
at times of peak demand

To generate electricity,
water is released from
an upper reservoir 
created by damming 
Little Back Creek. 

The water drops 
1,262 feet from 
the upper reservoir
to the lower reservoir. 

Water moves down 
through three tunnels, 
or "penstocks", 
carved through Little 
Mountain, which 
separates Little Back 
Creek and Back Creek. 

There are six turbines:
 Two at the bottom end 
of each of the three
penstocks. 

Turbines are reversible, 
and serve as uphill 
water pumps, as well 
as downhill water flow
electricity generators. 

The penstocks are 
3,780 feet long, 
and 28.5 feet 
in diameter.

They have 
concrete walls 
18-24 inches thick.

The water 
level in the 
upper reservoir 
can drop 
105 feet, 
and the 
lower reservoir 
can rise 
60 feet. 

The dam on 
Little Back Creek, 
creating the 
upper reservoir, 
is 460 feet high. 

The dam 
on Back Creek, 
creating the 
lower reservoir, 
is 135 feet high.



But ... 
a pumped storage 
station uses more 
electricity than 
it generates.

Pumping water to
an uphill reservoir 
requires 
more electricity 
than the turbines 
can generate when 
gravity is allowed 
to let the water 
go downhill to spin 
the six turbines 
on the way to the 
lower reservoir.

This Virginia plant 
is 80% efficient.

For every 
four kilowatts 
of electricity 
generated, 
five kilowatts 
are consumed.

The facility serves 
as a "battery", which 
can be started quickly 
as demand shifts, 
4,500 times per year. 

If the 
upper reservoir 
was fully drained, 
over 11 hours, 
it could produce 
24,000 megawatt
-hours of electricity.

The 500MW 
turbines 
can start 
exporting 
significant 
amounts 
of electricity 
into the grid 
within 5-10 
minutes. 
Note:
A coal-fired, 
or nuclear power
generating plant, 
would have 
long delays for 
"warming up". 

Peak power can be 
generated for only 
three hours. 

Once the 
upper reservoir 
has emptied, 
the turbines 
need to be 
reversed 
to pump water 
uphill and 
"recharge 
the battery."

Maximum 
power 
generation 
of 3,003MW 
is possible 
only when 
the reservoir
is full. 

As the
upper reservoir 
drains, the 
elevation of the 
water drops 
and the turbines 
spin at slower 
speeds.

The water flow is timed 
to provide electricity 
when demand peaks, 
typically in the summer 
when air conditioners 
kick on between lunch 
and early evening. 

At times of
low demand, 
such as
in the middle 
of the night, 
the water flow 
is reversed. 

The price of 
a kilowatt-hour 
of electricity 
sold in the 
afternoon 
is high. 

The cost of 
a kilowatt-hour 
used to pump 
water uphill 
before dawn,
is low.

Water flow 
when generating 
is 13.5 million 
gallons per minute. 

The flow when pumping 
uphill is slightly lower,
at 12.7 million gallons 
per minute.

During the summer, 
there may not be 
enough time to pump 
all the water back uphill 
before electricity demand 
rises again (and the flow 
needs to be downhill 
to generate power). 

Plant operators 
normally catch up 
by refilling the upper 
reservoir on the
weekends. 

When completely full, 
the upper reservoir 
has the capacity
to provide 24,000 
megawatt-hours 
of electricity. 



The Bath County 
Pumped Storage 
Station does not 
use fossil fuels 
to produce 
the electricity
it uses to pump
water uphill,
so it does not add 
greenhouse gases 
to the atmosphere.



Because water levels 
in the two reservoirs 
change so much, 
and so rapidly, 
they are not safe 
for recreational use. 

The two pumped 
storage reservoirs 
eliminated five miles 
of natural stream 
habitat.

The flooding 
of 950 acres 
and five miles of 
Little Back Creek 
and Back Creek 
was "offset" by  
Dominion Energy 
building two 
recreational ponds 
and a campground.

The recreational ponds 
offer warm water fishing 
opportunities for 
bass, sunfish, and 
channel catfish.



CONSTRUCTION:
The bedrock 
in the valley 
of Little 
Back Creek, 
in which the 
upper reservoir 
was constructed, 
is shale. 

The bedrock
in the valley 
of Back Creek,
in which the 
lower reservoir 
was constructed, 
is limestone. 

Little Mountain, 
through which
the "penstocks" 
were excavated, 
is also limestone.

When one 
of the penstocks 
carved through 
Little Mountain 
was first filled 
up with water, 
there was 
enough leakage 
and pressure 
changes through 
the limestone 
to buckle 
a steel liner 
in an empty, 
adjacent 
penstock. 

At Gathright Dam, 
grouting was injected 
into the bedrock
to seal it.




HISTORY:
In 1971, the 
Virginia Electric  and 
Power Company
        (VEPCO), 
now "Dominion Energy", 
obtained preliminary 
permits from the 
Federal Power 
Commission for two
pumped storage 
projects. 

They were for peak 
demand periods 
(typically from
11:00am  to  8:00pm), 
but would have
surplus capacity 
during nights.

Pumped storage was 
a proven technology, 
with a track record 
of meeting electricity
peak demand 
requirements 
in Virginia.

At the time,
natural gas 
prices were high 
( long before the 
fracking boom ),
otherwise a new
natural gas plant
would have 
been built.

Construction
started in 1977, 
but stopped 
three years later, 
because the growth 
in peak demand 
for electricity 
had not grown 
as projected 
by VEPCO. 

The utility 
then sold 
Allegheny
Power 
System 
(now FirstEnergy) 
a 40% share, 
and completed 
the construction.

Sharing the power, 
and the costs, 
made the Virginia
pumped storage
project feasible,
and it started 
generating 
electricity
in 1985.

National Public 
Radio titled a story 
on the project 
"The World's 
Biggest Battery."



Allegheny Power 
had proposed to build 
its own pumped storage 
project in West Virginia. 

The Federal Energy 
Regulatory Committee 
approved their pumped 
storage project, 
but the U.S. Army 
Corps of Engineers 
denied the needed
Clean Water Act 
Section 404 permit 
to allow construction.

And In 1988,
the Supreme 
Court finally 
ruled that the 
Corps' denial 
of that 
Section 404 
permit would 
stand.

Allegheny Power 
sold its 12,000 acres 
in Canaan Valley 
to the US Fish 
and Wildlife 
Service in 2002.